Posted tagged ‘Park View Rec Center’

Park View Field House Renovation Nearly Finished

August 7, 2015

This will probably be the final update on the Park View Field House at the recreation center before the project is completed. It is essentially completed now, and the majority of punch list items are expected to be completed by Wednesday, August 12, 2015, including removal of the temporary construction fence.

Below are photos of the (nearly) finished project.

Park View Field House

IMG_1158

IMG_1156

Park View rec center interior

IMG_1144

Park View Recreation Gets New Safety Netting

July 22, 2015

IMG_9156

A new wall of netting was installed at Park View Recreation Center on Tuesday to address the issue of soccer balls sailing into the covered seating area. This is an excellent addition and one that many have advocated for to date. The soccer field and basketball courts are heavily used and this addresses a longstanding safety issue.

Its also good to see the that the recreation center continues to be maintained and improved.

IMG_9154

Checking in on the Park View Field House Renovation

June 16, 2015

June Park View Field House(View of the field house from the southwest, showing new first floor windows.)

The renovation of the Park View Playground field house is coming along great. Anyone looking at the west elevation of the building will a good idea of what it will look like when work is completed, especially since the upper section has been painted and new windows have been installed.

Here are some completed/forecast project milestones for June:

  • June 10 – Gyp board was installed and prep for paint
  • June 12 – Exterior doors were installed
  • June 12 – Dormer windows on second floor installed
  • June 18 – Exterior paint will be complete
  • June 19 – Central air conditioning condensing unit will be installed
  • June 26 – New baseboard and flooring will be complete
  • July 6 – First floor windows will be installed

Below are two photos showing work in the loft area and the current state of the staircase.

20150603_113922_resized(New drywall in the loft area.)

IMG_0935a(The stripped stairway and new drywall in the east room.)

Park View Field House Renovation Update

May 15, 2015

IMG_8685

Based on a Department of General Services update issued on May 6, 2015, the Park View field house is moving along at a good pace and may even be a little ahead of schedule. The project currently has a budget of $439,390 and has the following project milestones.

Project Schedule Milestones
April 9, 2015 – KADCON mobilized to site
April 13 – Hazardous abatement began
April 17 – Hazardous abatement completed
April 24 – Roof construction began
April 27 – Demolition completed
May 22 – New roof to be complete
May 25 – New Walls to begin
May 29 – New windows to begin
June 8 – New ceilings to begin
June 15 – new finishes to begin
June 29 – New Millwork to be begin
July 31 – Substantial completion scheduled

In reviewing the project yesterday, the new roof has been completed, the porch is completely open now, the brickwork appears to be complete, and the old windows have been removed.

Much of the interior has also been gutted, thought the stairway up to the loft is to remain and be refinished. Below is an image showing the interior.

Park View field house(Stairway inside Park View field house May 14, 2015)

Restoration of Park View Playground Field House Begins

April 15, 2015

The work to renovate the historic Park View playground field house began on Monday, April 13, 2015, after the contract with KADCON was finalized at the end of March. The work that began on Monday encompasses hazardous abatement which will continue until April 24. Demolition work is scheduled to begin on April 27th. The entire project is aiming for a completion date of July 31st, 2015.

Park View field house

Park View Field House Renovations On Track for January

December 9, 2014
Field house at the Park View Rec Center in 2009.

Field house at the Park View Rec Center in 2009.

Here’s a brief update on where things stand with renovating the field house at the Park View Recreation Center. At this time:

  1. The construction drawings are 100% complete and have been submitted and approved by the Historic Preservation Office;
  2. The same construction drawings are currently being reviewed by DCRA so a building construction permit can be issued. It is anticipated that the permit will be issued anytime now;
  3. The RFP (request for proposal) was issued by the procurement office and a pre-proposal conference was held last week;
  4. A site walkthrough with interested bidders was held this past Friday (December 5);
  5. Contractor’s bids will be due on December 18th;
  6. Once bids are submitted, they will be reviewed and a contractor will be selected. The goal is to have a contractor on board by early January so the renovation can being mid to late January; and,
  7. A hazardous material survey will be performed while the building permit is under review and the contractor procurement is finalized.

This is all very promising, and I will continue to report progress as more details are known.

Details on the Park View Field House Renovation Project

October 1, 2014
The field house at the Park View playground as it neared completion on September 8, 1932

The field house at the Park View playground as it neared completion on September 8, 1932

Late yesterday, I received a list from the Department of Parks and Recreation that gives some insight into where things stand with the planned renovations to the historic field house at the Park View Recreation Center, as well as the scope of work that is to be undertaken.

Preserving, renovating, and putting the field house back into community use has been among my community priorities. I believe that restoring the structure and having it available for community use continues the progress we have already seen at Park View Recreation, and makes the playground much more flexible in supporting multiple groups using the center.

Funds to renovate the field house were a result of my testimoney on March 29, 2013, at the DPR Budget hearings.  Councilmember Graham briefly attended the hearing to lend his support for continuing the work already begun at Park View and announced the appropriation of $400,000 to renovate the structure on May 8, 2013.

Below is a list of what to expect with the Park View field house renovation in the coming months.

  • Queen Quinn Evans Architects has been retained to develop construction drawings for the renovation;
  • Queen Quinn Evans, DGS, DPR and HPO have been in communication in an effort to coordinate historical architectural details to make sure they are properly incorporated in the drawings;
  • Once drawings are complete, they will need to be submitted  to HPO for review and approval. It is anticipated that drawings will be submitted to HPO by late October;
  • The general scope of the work will consist of:
    • the removal of the porch enclosure to restore building’s historic integrity;
    • Restoration of exterior windows and doors;
    • Restoration of exterior brick;
    • Relocation of mechanical and electrical closets;
    • A new ADA compliant restroom;
    • Replacement of the roof;
    • Restoration of the interior stair case; and,
    • Installation of new finishes such as flooring, walls, light fixtures, etc
  • Upon HPOs approval, DGS will bid out the construction work to a general contractor for the construction and restoration.

I’m very excited about this and will share additional information as it becomes available.


%d bloggers like this: