Posted tagged ‘athletic fields’

Park View Athletic Field to be Repaired in Spring 2020

October 1, 2019

The Park View athletic field has been offline since June 20, 2019.

Yesterday, I received word from the Department of General Services (DGS) that the athletic field at the Park View Recreation Center will be repaired in the Spring of 2020 due to the availability of FY20 funding.

The field has been unavailable for sports use since June 20, 2019, when the DGS sent out notice that it was one of 13 fields that had failed their annual G-MAX testing.

While DGS had initially planned to move quickly with the repairs, a review of the scope of work needed for the field to be brought into compliance resulted in a need to secure funding. The reason DGS is waiting until the spring to undertake repairs is due to planning around weather.

This news actually comes at a good time, as the Park View UNC is hosting a Community Forum on the Safety of Playgrounds and Artificial Turf Fields in DC, sponsored by the Park View UNC and DC Safe Healthy Playing Fields at the Park View Rec Center on Wednesday, October 2nd, at 7 pm. More information on the event can be found here.

The athletic field at the Park View Recreation Center.

Athletic Fields at Park View Rec Center and Tubman Elementary School Fail Annual G-MAX Safety Tests

June 25, 2019

Park View Soccer Field is closed until repairs can be made to improve its safety.

On June 20th, the Department of General Services (DGS) sent out notice that they had begun their annual shock attenuation, or G-MAX testing, of the District’s 54 synthetic turf fields. As of last week, 13 fields had failed their G-MAX test out of 30 tested so far. Seven of the fields are in need of additional infill in order to return to compliance, however, six fields — including the athletic fields at Park View Recreation Center and Harriet Tubman Elementary School — will require more extensive repair.

All 13 fields were taken off-line immediately in order that the necessary adjustments and repairs could be made.  The extensive repair work could take up to two weeks; fields needing additional infill will require 1-2 days.

Below is the list DGS provided showing the fields that need to be repaired.

In speaking directly with DGS, I learned that they were scheduled to be on site at the Park View field on June 24th to inspect the field and assess the appropriate measures to repair the field and reopen it for community use.

You can read more about G-MAX and the testing at the DGS G-MAX webpage which includes the individual reports.