Update on Pepco’s Harvard Distribution Project

Yesterday Pepco shared that they are still on scheduled to complete their current round of construction near for the Harvard Substation Distribution Project by the end of March 2019. Since their public meeting on January 15th,  Pepco has continued its construction along Sherman Avenue and is currently finishing the manhole on Florida Avenue.

Moving forward into the next phase of work, Pepco held a meeting with DDOT and the construction team for The Wren (Wholefoods) development to discuss the next phase of work in the immediate areas along Florida and Sherman Avenues and coordinate the construction projects.

Following is a Summary of what was discussed at the Pepco Coordination Meeting:

  • DDOT inspectors reviewed Pepco TCP plans for the intersections of W Street/Florida Avenue as well as construction plans for The Wren Development;
  • Starting Monday, February 18th Pepco will begin excavation at W Street across Florida Avenue to connect conduit to the manhole currently being installed closets to the Florida/Sherman Avenue intersection;
  • Door hangers will be distributed along areas impacted as notification;
  • Construction will be during normal hours as defined DDOT;
  • Crews will ensure that steal plates are secured each night to avoid noise disturbance;
  • Pepco crews will coordinate with The Wren (crews) as they will need to install equipment needed for the new pedestrian signals that will be installed for access to The Whole Foods. This will be done as appropriate;
  • Once Pepco crews are complete with construction (March 2019), The Wren will then begin its construction to install the remainder of the equipment needed for signal installation;
  • Once The Wren has finished its construction, Pepco will then repave/resurface the intersection from curb to curb;
  • Once Pepco is ready to repave the road, crews will need to close one lane at a time in order to mill and pave the road. This should only be a 3 day operation and will be done once The Wren has completed its equipment instillation. They will do their own outreach to notify residents when construction wills start;
  • Crews are working to complete the remaining construction near the 2000 BLOCK of Sherman Avenue. Once this is complete Pepco will work to pave an mill the road in a similar fashion (one lane at a time). Pepco is currently revising their TCP’s to reflect safe accommodations along Sherman Avenue. Pepco will provide notice once they are ready to begin paving along Sherman Avenue. Crews are still on pace to complete construction along Sherman Avenue by May 2019; and,
  • Pepco still anticipates further construction on Sherman Avenue (north of Euclid), as well as Girard and Harvard Streets starting June 2019. Pepco will alert impacted residents in advance of any construction or if this time frame should change.

Below is a project overview sheet including a map of the impacted area for those who use Sherman Avenue.

Explore posts in the same categories: Restoration repair and maintenance, Streets and Trees

Tags: ,

You can comment below, or link to this permanent URL from your own site.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s


%d bloggers like this: